Property Insurance Claims Timelines Comprehensive Reference

Nationwide Sources dated Aug 2026 Download

Master 50-state + DC table of statutory and regulatory property claims handling deadlines: acknowledgment, investigation commencement, accept/deny decision, payment, and status-letter intervals, with the applicable day type (calendar, business or working days), catastrophe extensions, 'reasonably promptly' states, fastest and slowest timelines, statute-of-limitations notice requirements and a full regulation citation list. Every row was checked in August 2026 against the statute or regulation text and carries a citation. No rows are currently flagged as unverified.

Verification note (August 2026): every row checked against the current statute or administrative regulation text (state legislature and administrative code sites) and NAIC Model 902 where adopted; rows carry a citation/Source link. No states are flagged Figures in older metadata sections that conflicted with the verified table were removed. All master-table rows were verified against a primary source by the August 28, 2026 follow-up pass; none remain flagged.

Jump to section

Property Insurance Claims Timelines - All 50 States + DC

Purpose: Quick reference for statutory claims handling deadlines Last Updated: August 2026 (verified against statute and regulation text)


Important Notes

  1. "WD" = Working Days / "BD" = Business Days / "CD" = Calendar Days
  2. Many states use "reasonably promptly" without specific day counts
  3. Some states extend deadlines for catastrophe/disaster claims (see table below)
  4. Timelines may differ for health/auto vs. property claims — several figures previously listed here came from health-claim rules and have been removed
  5. Always verify current regulations - timelines can change

Verification: Every row in the master table links (Source column) to the primary statute or regulation that was checked. Cells reflect the text of that source as read; where a source sets no number, the cell says so rather than supplying one. Days are calendar days unless marked BD or WD. Where the official state site could not be fetched, the source link points to the reproduction that was used (e.g., Cornell LII), and confidence is noted in the second-pass verification note below.

Second-pass verification (Louisiana, Mississippi, New Jersey, New Mexico): These four rows were re-checked against official or reliable mirror text. Louisiana was read from the official legis.la.gov text of La. R.S. 22:1892 (§ 22:1973 is repealed, Acts 2024, No. 3, eff. July 1, 2024; the old 60-day rule no longer exists and no 90-day catastrophe figure exists). New Jersey was read from Cornell LII (nj.gov PDF still 404): the property decision deadline is 30 CD after POL, not 45. New Mexico's 90-day catastrophic figure is confirmed (§ 59A-16-20(F); 13.7.4 NMAC); no working-day acknowledgment figure exists, and 13.10.3 NMAC (previously cited) is a health rule. Mississippi has no numeric property deadline in § 83-5-45 or in Miss. Admin. Code Title 19 (mid.ms.gov itself could not be fetched; confidence medium).


Master Claims Timeline Table

State Acknowledge Begin Investigation Accept/Deny Payment Updates Regulation Source
Alabama 15 CD Prompt (forms within 15 CD) 30 days after POL (or policy period) 30 days after agreement 45 days 482-1-125 Ala. Admin. Code r. 482-1-125
Alaska 10 WD Prompt (forms on receipt) 15 WD after POL 30 WD after POL (undisputed) 45 WD 3 AAC 26.040/.070 3 AAC 26.070
Arizona 10 WD Complete within 30 days of notice 15 WD after POL 30 days 45 days R20-6-801 A.A.C. R20-6-801
Arkansas 15 WD Complete within 45 CD 15 WD after POL 10 WD after processed 45 CD Rule 43 Ark. Rule 43
California 15 CD Immediately, max 15 CD 40 CD after proof of claim 30 CD after acceptance 30 CD 10 CCR 2695.5/.7 10 CCR § 2695.7
Colorado Reasonably promptly Reasonably promptly 60 days after valid & complete claim 60 days after valid & complete claim Every 30 days after day 60 Reg 5-1-14 (3 CCR 702-5); § 10-3-1104(1)(h) Colo. SOS CCR
Connecticut Reasonably promptly Reasonably promptly Reasonable time after POL Prompt § 38a-816(6) C.G.S. § 38a-816
Delaware 15 WD 10 WD 30 days after POL Prompt (no number) 18 DE Admin Code 902 18 DE Admin. Code 902
District of Columbia Reasonably promptly Reasonably promptly Reasonable time Reasonably promptly § 31-2231.17 D.C. Code § 31-2231.17
Florida 7 CD Begin within 7 days after POL 60 days after notice 60 days after notice (interest after) § 627.70131 Fla. Stat. § 627.70131
Georgia 15 days POL forms within 15 days 60 days after POL (fire/EC); ≤60 days total 10 days after amount agreed Notice within 5 BD after deadline lapses Rule 120-2-52 Ga. Rule 120-2-52
Hawaii 15 WD Reasonable Reasonable time after POL 30 CD after affirmation HRS § 431:13-103(a)(11) HRS § 431:13-103
Idaho Reasonably promptly Reasonably promptly Reasonable time after POL Prompt § 41-1329 Idaho Code § 41-1329
Illinois 15 WD Reasonable Reasonable time 30 days after affirmation Delay letter at 75 days from report or 25 days after POL 50 IAC 919.40/.50/.80 50 Ill. Adm. Code 919
Indiana Reasonably promptly Reasonably promptly Reasonable time after POL Prompt IC 27-4-1-4.5 IC 27-4-1-4.5
Iowa 15 days Reasonable 30 days after POL 30 days after affirmation 45 days 191 IAC 15.41 191 IAC 15.41
Kansas 10 WD Complete within 30 days 15 WD after POL Prompt (no number) 45 days K.A.R. 40-1-34 K.A.R. 40-1-34
Kentucky 15 days Prompt (no fixed day count) 30 CD after POL (or notify why more time needed) 30 days after affirmation of liability (offer due within 30 CD of POL) 45 CD from notice, then every 45 CD 806 KAR 12:095 §§5-6 806 KAR 12:095
Louisiana No acknowledgment number; initiate loss adjustment within 14 days of notice Initiate loss adjustment within 14 days of notice (30 days catastrophic loss; commissioner may add up to 30 days by rule) Written settlement offer within 30 days after satisfactory POL 30 days after satisfactory POL; 30 days after written settlement agreement (50%/$1,000 penalty + fees if arbitrary) No periodic letter; field adjuster report within 15 days of request La. R.S. 22:1892 (§ 22:1973 repealed 2024) La. R.S. 22:1892
Maine Reasonable time after written notice Prompt (reasonable) Reasonable time after investigation 30 days after POL (60 days fire policies per §3002); 1.5%/month interest if overdue 24-A M.R.S. §2436 / §2436-A 24-A M.R.S. § 2436
Maryland 15 WD Written notice if not complete in 45 days 15 WD after properly completed claim forms Not specified (prompt settlement, Ins. §27-303) Every 45 days until coverage/damages determined COMAR 31.15.07.03-.04 COMAR 31.15.07.03
Massachusetts Reasonably promptly Reasonably promptly Reasonable time after POL Reasonably promptly M.G.L. c.176D §3(9) M.G.L. c.176D § 3
Michigan Prompt Specify POL materials within 30 days of claim No fixed deadline; 60 days after POL = timely payment threshold 60 days after satisfactory POL (12% simple interest thereafter) MCL 500.2006(3)-(4) MCL 500.2006
Minnesota 10 BD Complete and inform within 30 BD of notice (else state reason and expected date) 60 BD after POL 5 BD after agreement 10 BD reply to communications; no periodic letter Minn. Stat. §72A.201 subd. 4-5 Minn. Stat. § 72A.201
Mississippi No statutory number No statutory number No statutory number No statutory number for property (§83-9-5 prompt-pay is health only) None for property; Miss. Code §83-5-45 (unfair practices); no claims-timeline rule in Miss. Admin. Code Title 19 Miss. Code § 83-5-45 (FindLaw)
Missouri 10 WD Complete within 30 days of notice 15 WD after all forms/POL submitted Not specified for property (prompt settlement) 45 days from notice, then every 45 days 20 CSR 100-1.030/.040/.050 20 CSR 100-1
Montana Reasonable Reasonable 30 days after POL (60 days if additional info requested) 30 days after POL (10% interest if late) Mont. Code Ann. §33-18-232 MCA § 33-18-232
Nebraska 15 WD Begin within 15 WD 15 WD after POL (or notify why more time needed) 15 WD after claimant acceptance 30 WD from notice, then every 30 WD 210 NAC 60 §§006-008 210 NAC 60
Nevada 20 WD Begin within 20 WD; complete within 30 days 30 WD after POL 30 days after acceptance (interest per NRS 99.040 if late) 30 days from notice of delay, then every 30 days NAC 686A.665-.675 NAC 686A
New Hampshire 10 WD Commence within 5 WD 30 CD from notice of claim (delay letter if more time) 5 WD after agreement 30 days from delay letter, then every 30 days N.H. Admin. Code Ins 1002.05 N.H. Ins 1000
New Jersey 10 WD (10 WD reply to other claimant communications; 15 WD to Department inquiries) Prompt; forms/assistance within 10 WD 30 CD after properly executed POL (first-party non-auto); 45 CD third-party 10 WD after settlement agreement Delay notice, then every 45 CD until honored or rejected N.J.A.C. 11:2-17.6-.8 N.J.A.C. 11:2-17.7 (LII)
New Mexico Reasonably promptly Reasonably promptly Reasonable time after POL; catastrophic claims settled within 90 days after superintendent declares catastrophic loss and assigns claim number Prompt (no number) NMSA §59A-16-20; 13.7.4 NMAC (catastrophic claims) 13.7.4.11 NMAC (LII)
New York 15 BD (Reg 64) Commence within 15 BD (Reg 64) 15 BD after POL (Reg 64 §216.6(c)); 30 WD after POL (Ins. Law §2601(a)(4)) Not specified (prompt) Every 90 days while investigation incomplete 11 NYCRR 216 (Reg 64); Ins. Law §2601 N.Y. Ins. Law § 2601
North Carolina Reasonably promptly Prompt (reasonable standards) Reasonable time after POL Prompt (10 BD after settlement for motor vehicle only, 11 NCAC 04 .0421) G.S. 58-63-15(11) G.S. 58-63-15
North Dakota Reasonably promptly Reasonably promptly Reasonable time after POL Reasonable N.D.C.C. § 26.1-04-03(9) N.D.C.C. 26.1-04
Ohio 15 days Prompt (15-day response to communications) 21 days after POL 10 days after acceptance 45 days OAC 3901-1-54 OAC 3901-1-54
Oklahoma 30 BD (OAC) / 30 days (36 O.S. § 1250.6) 45 BD after POL (OAC 365:15-3-6) / 60 days (§ 1250.7) 45 BD after POL (OAC) / 60 days after POL (§ 1250.7, max 120) No numeric deadline 45 days (OAC) / 60 days (§ 1250.7) OAC 365:15-3-5 to -7; 36 O.S. §§ 1250.6-1250.7 OAC 365:15-3
Oregon 30 days 45 days after notice 30 days after POL No numeric deadline 45 days OAR 836-080-0225 to -0235 OAR 836-080-0235
Pennsylvania 10 WD 30 days after notice 15 WD after POL No numeric deadline 45 days 31 Pa. Code §§ 146.5-146.7 31 Pa. Code ch. 146
Rhode Island 15 days Prompt 21 days after POL 30 days after affirmation of liability 45 days 230-RICR-20-40-2 230-RICR-20-40-2
South Carolina Reasonably promptly Prompt (no number) Reasonable time No unreasonable delay S.C. Code § 38-59-20 S.C. Code § 38-59-20
South Dakota 30 days (acknowledge and act) Prompt (no number) Prompt Prompt SDCL 58-33-67(3) SDCL 58-33-67
Tennessee Reasonably promptly Prompt (no number) Reasonable time after POL Prompt (bad-faith penalty after 60-day demand, § 56-7-105) Tenn. Code § 56-8-105 (0780-01-05 is RESERVED) Tenn. R. 0780-01-05 (reserved)
Texas 15 days (30 BD surplus lines) 15 days (commence + request items) 15 BD after all requested items received (+45 days if extended; 30 days arson) 5 BD after notice of acceptance Tex. Ins. Code §§ 542.055-542.059 Tex. Ins. Code ch. 542
Utah 15 days 15 days (forms/assistance) 30 days after POL 30 days after POL (if liability clear) 45 days R590-190-6, -9, -10 Utah R590-190
Vermont 10 BD Prompt 15 BD after POL (first-party) 10 BD after settlement agreed 30 BD (third-party only; first-party none) Reg. I-1979-02 (Rev.) §§ 5-6 Vt. Reg. I-1979-02
Virginia 15 CD Prompt (45-CD delay notices) 15 CD after POL No numeric deadline 45 CD 14VAC5-400-50, -60 14VAC5-400-60
Washington 10 WD 30 days after notice 15 WD after POL 15 BD after signed release/settlement docs 30 days WAC 284-30-330, -360, -370, -380 WAC 284-30
West Virginia 15 WD 15 WD 10 WD after investigation (delay notice if >30 CD from POL) 15 WD after agreement 45 CD W. Va. Code R. § 114-14-5, -6 W. Va. Code R. § 114-14
Wisconsin 10 consecutive days Reasonable dispatch Reasonable time after POL 30 days (7.5% interest) Wis. Admin. Code Ins 6.11; Wis. Stat. § 628.46 Wis. Stat. § 628.46
Wyoming Prompt Prompt 45 days after receipt of claim and supporting bills 45 days (same clock) Wyo. Stat. § 26-15-124(b) Wyo. Stat. tit. 26

Catastrophic/Disaster Timeline Extensions

State Standard Catastrophe Extension Notes
Florida 60 days after notice Up to 30 additional days OIR may extend by order (§ 627.70131)
Texas 15 BD after items received All deadlines + 15 days Weather-related catastrophe / major disaster (§ 542.059(b))
Louisiana Initiate loss adjustment within 14 days of notice 30 days for catastrophic loss; commissioner may add up to 30 days by rule; one further extension needs legislative committee approval Catastrophe changes only the initiation window; 30-day POL payment/offer clock unchanged (§ 22:1892(A)(3)); catastrophic first-party immovable-property penalties under § 22:1892.2
New Mexico Reasonable time Settle each catastrophic claim within 90 days after declaration and claim-number assignment § 59A-16-20(F); 13.7.4.11 NMAC (eff. 3/1/2023); applies to property and vehicle physical damage claims

Colorado's former "60 WD catastrophe" entry was removed: no such extension appears in Reg 5-1-14 or § 10-3-1104(1)(h).


States with "Reasonably Promptly" Standards (No Specific Days)

State Regulation Notes
Colorado Reg 5-1-14; § 10-3-1104(1)(h) Prompt acknowledgment; 60-day decision/payment clock
Connecticut § 38a-816(6) No day counts for property; 30/20/60-day figures are health-only (§ 38a-816(15))
District of Columbia § 31-2231.17 All timelines = "reasonably promptly"
Idaho § 41-1329 No specific day counts
Indiana IC 27-4-1-4.5 No day counts; numeric deadlines apply to health claims only (IC 27-8-5.7)
Massachusetts M.G.L. c.176D § 3(9) "Reasonably promptly" throughout
Mississippi § 83-5-45 No property day counts (§ 83-5-45 and Miss. Admin. Code Title 19 checked); § 83-9-5 prompt-pay is health only
New Mexico § 59A-16-20 "Reasonably promptly"; only numeric is 90 days for declared catastrophic claims (§ 59A-16-20(F))
North Carolina G.S. 58-63-15(11) No property day counts; 30/45-day rules are accident/health only
North Dakota N.D.C.C. § 26.1-04-03(9) No day counts anywhere
South Carolina § 38-59-20 "Reasonable promptness" only
Tennessee § 56-8-105 Rule 0780-01-05 is reserved; only numeric is 15 CD to furnish forms

Fastest Required Timelines

Acknowledgment (Fastest)

  1. New Hampshire - 10 WD (investigation must commence within 5 WD)
  2. Florida - 7 CD
  3. Alaska - 10 WD
  4. Arizona - 10 WD
  5. Kansas / Missouri / Pennsylvania / Washington - 10 WD
  6. Minnesota / Vermont - 10 BD
  7. Wisconsin - 10 consecutive days

Accept/Deny Decision (Fastest)

  1. Vermont - 15 BD after POL (first-party)
  2. Virginia - 15 CD after POL
  3. Alaska, Arizona, Arkansas, Kansas, Maryland, Missouri, Nebraska, Pennsylvania, Washington - 15 WD after POL
  4. New York - 15 BD after POL (Reg 64); 30 WD after POL (§ 2601)
  5. Texas - 15 BD after all requested items received

Payment (Fastest)

  1. Minnesota - 5 BD after agreement
  2. Texas - 5 BD after notice of acceptance
  3. New Hampshire - 5 WD after agreement
  4. Ohio - 10 days after acceptance
  5. Georgia - 10 days after amount agreed
  6. Arkansas / Vermont - 10 WD / 10 BD

Slowest/Most Lenient Timelines

Accept/Deny Decision (Slowest)

  1. Oklahoma - 60 days after POL under 36 O.S. § 1250.7 (max 120); 45 BD under OAC
  2. Colorado - 60 days after valid and complete claim
  3. Florida - 60 days after notice (+ up to 30 days by OIR order)
  4. Georgia - 60 days after POL (fire/extended coverage)
  5. Minnesota - 60 BD after POL
  6. Michigan - no fixed deadline; 60 days after POL is the timely-payment threshold (12% interest)
  7. Montana - 30 days after POL, 60 if additional information requested

Tennessee (formerly listed at 60 days) has no numeric decision deadline. Louisiana's catastrophe rule only extends loss-adjustment initiation (14 to 30 days); New Mexico's 90-day catastrophic settlement deadline is confirmed.


Update/Status Letter Requirements

Frequency States
30 days CO (every 30 days after day 60), NV, NH, WA
30 WD / BD NE (30 WD), VT (30 BD, third-party only)
45 days AL, AZ, AR (45 CD), IA, KS, KY, MD, MO, NJ (45 CD), OH, OK (OAC; 60 days under § 1250.7), OR, PA, RI, UT, VA (45 CD), WV (45 CD)
45 WD AK
90 days NY
Event-based CA (30 CD), GA (notice within 5 BD after deadline lapses), IL (delay letter at 75 days from report or 25 days after POL), MN (10 BD reply to communications)
Not specified CT, DC, DE, FL, HI, ID, IN, LA (field adjuster report within 15 days of request only), ME, MA, MI, MS, MT, NM, NC, ND, SC, SD, TN, TX, WI, WY

Removed from earlier lists: IL, IN, KS, MN (no 30-day cycle); GA, SC (no 45-day cycle); TN (no 60-day cycle); FL (no 45-day cycle). Utah's status letters have no public-adjuster/attorney waiver — that exception applies to the SOL notice.


SOL Notice Requirements

Some states require insurers to notify claimants of approaching statute of limitations:

State Notice Requirement
Alabama ~45 CD before SOL expiration
Alaska 60 CD before expiration
Arizona 30 days (first-party) / 60 days (third-party)
Kansas 30 days (first-party) / 60 days (third-party)
Missouri 30 days (first-party) / 60 days (third-party)
Nevada 60 days before expiration
Ohio 60 days before SOL expiration
Oklahoma 30 days (first-party) / 60 days (third-party) (OAC 365:15-3-7(e))
Oregon 30 days (first-party)
Utah 60 days (R590-190-10(3); waived if represented by PA/attorney)
Vermont 30 BD (first-party) / 60 BD (third-party) before expiration
West Virginia 30 days (first-party) / 60 days (third-party) (§ 114-14-6.12)

Key Observations

  • Numbers previously borrowed from health-claim rules (CT, IN, NC) and figures with no basis in the cited text (CO 15/30/15 WD, IL uniform 30 days, SC 15/30/30/45, TN 30/60, NY 35 BD payment, OK 20 BD acknowledgment) have been removed.
  • Payment deadlines are less common than decision deadlines. DE, KS, MD, MO, NY, OK, OR, PA, and VA set no numeric payment deadline; they require prompt payment only.
  • Florida was tightened in 2022 (SB 2-A): 7-day acknowledgment, 60-day pay-or-deny, and no 45-day update cycle.
  • Interest rates: MI 12% (after 60 days from POL), MT 10%, ME 1.5%/month, WI 7.5% (no longer 12%), TX 18% plus fees after 60 days, WY 10% plus attorney fee for unreasonable refusal.
  • Day type matters: NE and AK count working days for everything; AL, UT, and VA are expressly calendar days.

Key Regulation Citations

State Regulation
AL 482-1-125
AK 3 AAC 26.040/.070
AZ R20-6-801
AR Rule 43
CA 10 CCR 2695.5/.7
CO Reg 5-1-14 (3 CCR 702-5); § 10-3-1104(1)(h)
CT § 38a-816(6)
DE 18 DE Admin Code 902
DC § 31-2231.17
FL § 627.70131
GA Rule 120-2-52
HI HRS § 431:13-103(a)(11)
ID § 41-1329
IL 50 IAC 919.40/.50/.80
IN IC 27-4-1-4.5
IA 191 IAC 15.41
KS K.A.R. 40-1-34
KY 806 KAR 12:095 §§5-6
LA La. R.S. 22:1892 (§ 22:1973 repealed 2024)
ME 24-A M.R.S. §2436 / §2436-A
MD COMAR 31.15.07.03-.04
MA M.G.L. c.176D §3(9)
MI MCL 500.2006(3)-(4)
MN Minn. Stat. §72A.201 subd. 4-5
MS None for property; Miss. Code §83-5-45 (unfair practices); §83-9-5 prompt-pay is health only
MO 20 CSR 100-1.030/.040/.050
MT Mont. Code Ann. §33-18-232
NE 210 NAC 60 §§006-008
NV NAC 686A.665-.675
NH N.H. Admin. Code Ins 1002.05
NJ N.J.A.C. 11:2-17.6-.8
NM NMSA §59A-16-20; 13.7.4 NMAC
NY 11 NYCRR 216 (Reg 64); Ins. Law §2601
NC G.S. 58-63-15(11)
ND N.D.C.C. § 26.1-04-03(9)
OH OAC 3901-1-54
OK OAC 365:15-3-5 to -7; 36 O.S. §§ 1250.6-1250.7
OR OAR 836-080-0225 to -0235
PA 31 Pa. Code §§ 146.5-146.7
RI 230-RICR-20-40-2
SC S.C. Code § 38-59-20
SD SDCL 58-33-67(3)
TN Tenn. Code § 56-8-105 (0780-01-05 is RESERVED)
TX Tex. Ins. Code §§ 542.055-542.059
UT R590-190-6, -9, -10
VT Reg. I-1979-02 (Rev.) §§ 5-6
VA 14VAC5-400-50, -60
WA WAC 284-30-330, -360, -370, -380
WV W. Va. Code R. § 114-14-5, -6
WI Wis. Admin. Code Ins 6.11; Wis. Stat. § 628.46
WY Wyo. Stat. § 26-15-124(b)

Disclaimer: This table is for reference only. Timelines can change by regulation or legislation. Always verify current law before relying on these deadlines.

Last Updated: August 2026 (verified against statute and regulation text)

More Reference Tables